City of Cleveland Water Department - Financial & Management Consulting
Challenge:
In 2008, Cleveland Water faced serious operational hurdles:
- 18% of bills were estimated, frustrating customers.
- Manual meter readings and a CIS upgrade created inefficiencies.
- Most meters were indoors, making access difficult.
- Rising costs and a shrinking customer base strained resources.
Solution:
IBS, in partnership with Black & Veatch, supported the city’s $115M Clear Reads AMR project with:
- Project & Contract Management - Oversight of vendors, budgets, and timelines.
- Policy Development - Created Access, Opt-Out, and Claims policies to streamline installations.
- Quality Assurance & Field Oversight - Daily exception reviews, site visits, and SOP improvements.
- Financial Modeling & Analytics - Forecasting, rate modeling, and forensic audits to uncover revenue opportunities.
- Technical Support - Helped manage one of the fastest indoor meter installations in the U.S.—over 1,300 meters/day.
Impact:
- Estimated bills reduced from 18% to under 1%
- Customer satisfaction improved
- Data-driven decision-making enabled
- Operational efficiency and revenue recovery enhanced